1. What is the required period for posting the OSHA 300A Summary annually?

A February 1 to April 30 B April 1 to June 30 C January 1 to March 31 D March 1 to May 31

2. Which item is included in the Safety Manual Package?

A OSHA Inspection Quick Tips Card B Fire Prevention Plan C Medical Contact Information D Emergency Action Plan

3. What type of fire extinguisher is required at the Compliance Center?

A Foam fire extinguisher B Water-based fire extinguisher C Three- to five-pound ABC fire extinguisher D Carbon dioxide fire extinguisher

4. What should be posted to give directions to the nearest medical facility?

A Contractor/Supplier Contact Info B Project Emergency Phone List C Emergency Action Plan D Medical Contact Information

5. What is required to be posted in a conspicuous location close to the main construction traffic entrance?

A SWPPP sign B Emergency Action Plan C BMP Map D Washout Signage

6. What is the minimum height at which guardrails are required on working platforms in California?

A 8 feet B 10 feet C 7.5 feet D 6 feet

7. What is the maximum spacing allowed for stud bay in clear story framing with 2 rows of blocking?

A 24" o.c. B 16" o.c. C 20" o.c. D 18" o.c.

8. How much force must guardrails be able to withstand in all directions?

A 300 lb. B 200 lb. C 250 lb. D 150 lb.

9. What material is required for window and door guards?

A 1x4 material or better B 2x4 material or better C 2x2 material or better D 3x4 material or better

10. What is the maximum intended load for pump jack scaffolds?

A 400 pounds B 600 pounds C 500 pounds D 700 pounds